Unit 4 action Plan
The unit 4 action plan is a checklist of all of the items that need to be completed and how long each section will take to complete, This is to help the organization of the pre-production and to give me a structure to follow.
Unit 4 action plan
Task to complete | Time to complete |
Case studies | Start date (9th Nov) |
Film concept ideas | 6 days (15th Nov) |
Above the line and below the line | 1 day (16th Nov) |
Film pitch | 2 days (18th Nov) |
Film treatment | 1 day (19th Nov) |
Script writing | 6 days (25th Nov) |
Storyboard | A week (Dec 2nd) |
Shot list | 3 days (Dec 5th) |
Funding table | 2 days (Dec 8th) |
Budgeting | 3 days (Dec 11th) |
Location recce | 5 days(Dec 16th) |
Email for permission | 1 day (Dec 17th) |
Production schedule | 5 days (Dec 22nd) |
Cast and crew table | 4 days (Dec 26th) |
Cast and crew release forms | 1 day (Dec 27th) |
Call sheet | 1 day (Dec 28th) |
Contingency plan | 2 days (Dec 30th) |
Risk assessment | 6 days (Jan 5th) |
Equipment booking | 2 days (Jan 8th) |
Evaluation |
|
Pre-production report |
|
Start date: 9th November 2020 End date: 22nd March 2021